I need to obtain some information on fire-retardant-treated roof trusses.

I have a 29 x 72 mobile office with a 2-foot deep wooden truss above the ceiling that a client is required to sprinkler. Is there any way to avoid sprinklering above the gypboard ceiling?

I am a building inspector and I have a question on information provided on truss design drawings. What does the uplift reaction number represent? Some manufacturers are very specific and state “to provide for mechanical connection of the truss to the top plate with a connector capable of withstanding a specific load.” Others simply list the uplift reaction with no further information. These are the ones that have caused a debate as to what the number actually represents.

Is there a detailed table for gable studs that gives the maximum length a vertical member can be before a lateral brace is required?

Can a roof truss penetrate a one-hr. tenant separation wall without having a one-hr. rated ceiling? The building official insists that the 2x4 chords are combustible and nullify the integrity of the one-hr. rated partition that is constructed in an attic above an 8 in. C.M.U. bearing wall. The partition consists of gypsum board attached to 2 x 4 stud framing. The building official insists that a ledger must be attached through the gypsum board to support the trusses each side of the wall. This is almost saying that any rated assembly must have bearing only on other rated assemblies.

We are currently developing a project which specifies “Seismic Design Category C.” We are an East Coast truss manufacturer and have not encountered seismic requirements before.

Are wood trusses designed to be fall protection anchors that would support a worker should he fall?

How much OSB can be stacked on a floor deck without damaging the trusses?

In RC 2601, is RC-1 Channel used?

When you’re selling trusses through a lumberyard and the contractor calls to say that the “trusses don't fit correctly,” who has the ultimate responsibility for the trusses? I argue that the lumberyard is responsible since we have provided them with all the information on how the job was designed, even though they may or may not have passed this information on to the contractor.